Ebinger v. Venus Construction Corp.

by
In 1995, Charles and Charlene Ebinger contracted with Venus Construction Corporation to build a home. The couple moved into their new residence in 1997. In 2003, the Ebingers filed suit against Venus alleging defects in the home's foundation. Venus sought indemnification from one of its subcontractors. At issue in this case is whether the construction company's third-party demand against its subcontractor was time-barred by state law that established a peremptive period for actions against residential building contractors. The peremptive period was established originally at ten years, but subsequent amendments shortened its duration. A 1999 amendment reduced the period to seven years; a 2003 amendment reduced it to five years. Upon consideration of the trial record and the applicable legal authority, the Supreme Court found that the latest version of the statute applied in this case (2003). Consequently, the court held that the construction company's right to indemnity from its subcontractor was extinguished and its third party demand was perempted. View "Ebinger v. Venus Construction Corp." on Justia Law